Works on assembly of all process equipment have been completed at the construction site in Orenburg. 90 % of construction works are completed. Interior finishing and placement of the Automated Control System (ACS) cabinets is in progress.
Individual tests of process pipelines and equipment have been commenced.
Preparation to the project handover to the State Inspection is in progress.
Commissioning works are planned for the beginning of March 2014. Cryogastech LLC specialists perform development of the Process Regulations and Commissioning Guidelines.